Skip to main content
Loading…
This section is included in your selections.

There is a charge for temporary service for new construction requiring only a service drop and meter setting, which is as follows:

$ 75.00 for single-phase service

150.00 for three-phase service

The amount of the charge shall be paid at the time of request for service. Such temporary service, when overhead, must be attached to a secured structure and have the state electrical inspection tag before connection. Where possible, the location of the temporary service should be such that it can be also used with a minimum of alteration for the permanent service. Other temporary service requires a deposit equal to the City’s costs. (Ord. 2128 § 5, amended, 1981; Ord. 1865, amended, 1975)